The Derry Township Municipal Authority (DTMA) entered into a contract with Ankiewicz Enterprises, Inc. (Ankiewicz)
to construct the Ridge Road Drainage Improvements Project (Project). The Project involves the replacement, upgrade,
expansion and a degree of relocation of a large diameter storm sewer system extending from Spring Creek near
Hersheypark, along Park Boulevard and Ridge Road, at the Ridge Road and West Chocolate Avenue intersection, and
then south along Ridge Road to West Caracas Avenue. This project is an effort by DTMA to reduce flooding in this area
during heavy rain events and to ensure vehicular and pedestrian safety.
Work drilling a new 48-inch diameter storm sewer beneath and across the Norfolk Southern Railroad had proven to be
extremely difficult and resulted in delays, but was eventually completed. Significant and extensive rock excavation
during all phases of the Project also hindered the pace of the work. However, Ankiewicz has completed the installation
of all storm sewers and inlets throughout the entire Project length, along with curbing and sidewalk replacement!
What still remains is some minor restoration work and final pavement replacement. Final pavement replacement
throughout the Project length, including the crosswalks on West Chocolate Avenue, will begin on May 5th at the Ridge
Road and West Caracas Avenue intersection.
Pavement replacement will require localized, short-duration road closures as this work progresses along Ridge Road
from West Caracas Avenue north to Park Boulevard. Detour signs will be in place to notify and reroute vehicular and
pedestrian traffic accordingly. For safety, DTMA strongly urges pedestrians and vehicular traffic to obey detour signs
during this critical final stage of the Project work.
As a recent addition to the project, DTMA partnered with the Township to install new sidewalk, ADA ramps and
crosswalks on Ridge Road between West Chocolate Avenue and West Caracas Avenue. This was not part of the original
Project scope, but was a valuable additional improvement to pedestrian traffic in this area!
DTMA anticipates that the Project will be completed in its entirety in early June.